Cheltenham Site Completion

The site is now all but complete.  The units look amazing.  The final snagging matters will continue for a number of days, which is normal, but the road on Bloomsbury Street is now to get its top coat this Wednesday.

dsc_0820

The units are now selling fast.  I think the election caused some uncertainty amongst buyers but they are now out in force and we expect the units to be all sold (STC) by next week.

 

Regards,

Mick Rawlinson

 

 

 

 

 

 

 

Continue reading

Cheltenham Site Update

We’re almost there, with the final trades working hard to get the units finished.

dsc_07941

 

The render looks amazing and is designed to reduce maintenance and enhance durability.

dsc_07781

The kitchens are arriving as and when required and being fitted now.

dsc_07831

 

High quality fittings have been used throughout the properties, with simple but effective touches like soft closing toilet seats.  The internal doors in particular are extremely high quality giving the feel of contemporary luxury and solidity.

dsc_07922

 

Regards,

Mick Rawlinson

 

 

Continue reading

Cheltenham Site Update

The plan is to finish on site by the end of March, but some of the houses will be built complete early March.

All trades are working well together to complete first and second fix like plumbing and electrics.

The final major works are to the road on Bloomsbury Street.  We have the local authority’s permission to close the road to get the turning head complete imminently.

The render is now complete to plots 3,4,5,6.

 

c25-0011

 

Regards,

Mick Rawlinson

 

Continue reading

Cheltenham Update

The site at Cheltenham is a very busy place to be with up to 30 contractors working on the project at peak times.  We are looking to complete the build mid to late March 2015.  First fix is just about to complete internally and the bricklayers are charging ahead externally.

dsc_07271

The main change since the last visit is the staircases are in.  There was a slight issue in that the original product was to the wrong dimensions, but credit to the manufacturers for replacing them quickly.

dsc_07281

Half of the units have been boarded ready for plastering.

dsc_07321

The next big event is the road closure on Bloomsbury Street, during which we’ll install the turning head.  Before we can do this we’ll complete the rendering and brickwork to the effected units.  The plan is to complete the turning head quickly to minimise disruption to the neighbours.  The neighbours have been very supportive of the project.

 

Regards,

Mick Rawlinson

img_19291

Continue reading

Cheltenham Site Update

Thankfully the sites all survived the Christmas break, and actually some of the site teams continued to work through the break period.

It is now a really busy period in that we have 2 weeks to clear the scaffolding from units 3 to 9 in preparation of the road closure at Bloomsbury Street, so that we can get the turning head constructed.  Before that we have to complete the brickwork on the properties on both sides of the turning head

dsc_07161

The timber frames are now all delivered and installed and the supplier is finishing the snagging list.

dsc_07072

The insulation arrives on an articulated lorry Today for all the units and a team start Monday to install it.

dsc_07181

 

The agents have been generating huge interest in the units and we are discussing various offers.

 

Regards,

Mick Rawlinson

 

 

Continue reading

Cheltenham Site Update

The team are preparing the site for the Christmas break.

Gas, water and electricity supplies are booked for January 2015

The final timber frame for units 10 & 11 have been erected.

The roofing is now complete at units 7, 8, 9, and work has started at units 1 and 2.

The block work is under way around units 3,4,5 & 6.  We have now sourced 18,000 bricks which will be sufficient for most of the project.

chelt-22-0111

It is likely we’ll be fitting ultra efficient air conditioning systems which can be controlled from mobile telephone apps or a tablet.  More to follow on this subject.  They will replace the gas Central Heating that we initially looked at.

I intend to be on-site first week of 2015, so will send another update thereafter.

 

Regards,

Mick Rawlinson

 

Continue reading

Cheltenham Site Update

The race is on to make the site wind and water tight.  The rain hasn’t stopped and it’s concerning.  We need to protect the chipboard floors from moisture and all the other timber on site.

The roofing contractors have had an issue matching the roof at plot 7 against plots 8 and 9, but this has now been resolved.  There was a slight issue with the dormers at plots 8 and 9, but again it has been resolved.

The brick layers begin work on plots 10 and 11, on or about 25 Nov 14.

cheltenham-19-001-11 cheltenham-19-0081

 

Regards,

Mick Rawlinson

 

Continue reading

Cheltenham Site Update

The school holidays are over and the heavens have opened, but I’m pleased to say rain hasn’t yet caused any major problems on-site at Cheltenham.  There is a slight delay but the Site Agents’ are looking at ways we can make up time.  In previous reports we looked at the ‘bases’ going in and this bulletin concentrates on the arrival of the timber frames.  The frames are the single biggest costs at the site, so it’s a relief to have them on-site and in-place.  They came from a factory in Wales on the back of a lorry and have been craned in to place.

chelt-0031

We’ve also received the first draft of the Computer Generated Images (CGI) which we’ll use to help the selling agents promote the site.  We’ll upload the final images when we get them.

chelt-0091

The local authority representatives and our Party Wall Surveyor have met on-site and agreed a process to deal with Party Wall matters and the Honeybourne Line.

 

 

Regards,

Mick Rawlinson

 

Continue reading

© 2017 Bastien Jack. All Rights Reserved