Phoenix House Phase 2 update – Sept 15

After planning permission was granted to provide two penthouse flats in the roof void and two new three storey Townhouses at the end of Phoenix House, work started at a pace.

Despite the wettest August in a century with rainfall in West Sussex totalling 144.2mm, the team have progressed very well with Phase 2 and are ahead of programme!

Reduce levels excavated and set out to receive raft foundations for the new Townhouses

img_0667-1                                           img_0668-1

Lightweight Steel Frame for one of the townhouses…. and a day later already up to second floor

img_0727                       img_0724

Roof space being prepared and initial install of the new steelwork to accommodate five new dormers and balconies serving the Penthouses

img_0728               img_0729

img_0671-1

Marketing details have just been released for the Townhouses and are being sold locally by Cubitt & West Estate Agents

 