Phoenix House Phase 2 update – November 15

We are in the final stages of Phase 2 Phoenix House and delighted to confirm we are on programme despite some awful unseasonal weather for the South East.  The Townhouses have 1st fix electrics completed while plumbing is nearing the end of its 2nd fix.  Externally we are well on with the external finishes and will be aided further when the scaffold is removed.

The penthouses are also well on with the separating wall and internal partitions in place.  1st fix electrics are also complete and plumbing as the townhouses nearing 2nd fix completion.  We are ready to commence skimming and plastering!

file_002-9 file_001-6 file_006-8

The site has evolved significantly as we fully engage with new build and conversion around already completed and occupied Phase 1.  Careful consideration has been given to our new occupiers as we co habit the site, daily briefings are  provided via notices in the lobby and daily due diligence and Health & Safety risk analysis is conducted by our Site Manager.

file_008-5 file_000-10 file_003-8-e1448225861424

Regards

Rick Nicholls

Operations Manager

bastien-250

Continue reading

Phoenix House Phase 2 update – Sept 15

After planning permission was granted to provide two penthouse flats in the roof void and two new three storey Townhouses at the end of Phoenix House, work started at a pace.

Despite the wettest August in a century with rainfall in West Sussex totalling 144.2mm, the team have progressed very well with Phase 2 and are ahead of programme!

Reduce levels excavated and set out to receive raft foundations for the new Townhouses

img_0667-1                                           img_0668-1

Lightweight Steel Frame for one of the townhouses…. and a day later already up to second floor

img_0727                       img_0724

Roof space being prepared and initial install of the new steelwork to accommodate five new dormers and balconies serving the Penthouses

img_0728               img_0729

img_0671-1

Marketing details have just been released for the Townhouses and are being sold locally by Cubitt & West Estate Agents

 

Rick Nicholls